North Cr Culvert Replacement at Harborview Dr
#21-1549 DK04 (a) #21-1549 DK04 (a)
Organization West Sound Partners for Ecosystem Recovery
Sponsor Gig Harbor Public Works
Status Active
Schedule Start Date: 1/15/2025 End Date: 6/1/2026
Category Category: Planning
DESCRIPTION
In 2012 the City of Gig Harbor removed a 300 LF fish barrier at the mouth of the City's North Creek, (aka Donkey Creek) by removing a 36-inch dia. culvert and replacing it with natural streambed and a bridge at North Harborview Dr. The City's proposed North Creek Culvert Replacement Project is now intended to remove two additional fish barriers.  Barrier #1 is an identified barrier at Harborview Dr. (WDFW Site 105 K053021a), which is immediately upstream of the City's 2012 fish barrier removal project. Barrier #2 is associated with an unnamed tributary to North Creek that currently flows more than 450 LF through a series of catch basins and storm pipes but is not identified by WDFW.  See the attached North Creek Project Detailed Site Map.  Both locations anticipate using the Washington State streamlined process for fish habitat enhancement projects, including replacing the existing fish barriers with natural stream beds.  The City anticipates completing a separate feasibility study for these two locations in fall 2022 to provide culvert replacement alternatives, establish a project schedule, and provide conceptual cost estimates. This project proposal is for design and permitting of the City Council's recommended alternative based on the pending feasibility study.
Show more  ↓
FUNDING SOURCES
FUNDING ENTRIES FROM GRANT PROJECT AGREEMENT
TypeDateFunding OrgFunding ProgramMatchAmount
Requested01/13/2022Gig Harbor Public WorksMatch$70,000.00
Requested01/13/2022Recreation and Conservation Office (RCO)BA Fish Barrier Removal Board$350,000.00
Allocated12/05/2024Gig Harbor Public WorksMatch$70,000.00
Allocated12/05/2024Recreation and Conservation Office (RCO)BA Fish Barrier Removal Board$350,000.00
Spent05/05/2025Gig Harbor Public WorksMatch-$60,921.19
Spent05/05/2025Recreation and Conservation Office (RCO)BA Fish Barrier Removal Board-$304,605.97
Grant Project Agreement Totals Proposed Requested Allocated Spent Balance
$420,000.00 $420,000.00 $420,000.00 $365,527.16 $54,472.84
OTHER FUNDING (Funding that is NOT in a grant project agreement)
TypeDateFunding OrgFunding ProgramMatchAmount
Other Funding Totals Requested Allocated Spent Balance
Grand Totals Proposed Requested Allocated Spent Balance
PRIMARY SPONSOR
PROJECT CONTACT
ALT PROJECT CONTACT
PROJECT MANAGER
PHOTOS

 
LOCATION
Chinook-Pop (ESU):Chinook-Puget Sound, Threatened
Chum-Pop (ESU):Chum-Puget Sound/Strait of Georgia, Not Warranted
City Areas:Gig Harbor
Coho-Pop (ESU):Coho-Puget Sound/Strait of Georgia, Species of Concern
County:Pierce
HUC12:Curley Creek-Frontal Colvos Passage (171100190703)
HUC8:Puget Sound (17110019)
Lead Entity Area:West Sound Watersheds
Legislative District:26
Pink-Pop (ESU):Pink-Odd Year, Not Warranted
Puget Sound Action Areas:North Central Puget Sound
Salmon Recovery Regions:Puget Sound
Sections:06
Steelhead-Pop (ESU):Steelhead-Puget Sound, East Kitsap Peninsula Tributaries, Threatened
Township:T21NR02E
Watershed Administrative Unit:Clovos Passage/Carr Inlet
WRIA:Kitsap
View project on a larger map